THE BOLINAS-STINSON
UNION SCHOOL DISTRICT
PROPOSED LONG-RANGE PLANNING PROCESS TIMELINE
Return to Table of Contents
|
Activity
|
Responsible Party
|
Projected Date to be Accomplished
|
Progress to Date/
Date Completed
|
Staff/parent/community survey:
-
Survey data compiled and presented to Board
|
School
Site Council
|
May 12, 1998
|
June 2, 1998
|
Designate Planning Team Composition
for presentation to the Board for approval.
|
School
Site Council
|
May
12, 1998
|
May
19, 1998
|
First Planning Team retreat:
- Develop belief statements
- Develop mission statement
- Identify strengths and challenges of B/S SD
|
School Site Council
Planning Team
Planning Team
Planning Team
|
By
June 6, 1998
|
June
19, 1998
|
|
Report
to the Board on Beliefs, Mission and strengths and challenges:
|
Planning
Team
|
June
9, 1998
|
June
23, 1998
|
Second
Planning Team retreat:
- Identify focus area
- Compose action teams
|
Planning
Team
|
By
July 10, 1998
|
September
10, 1998
|
|
Report
to the Board on Action Teams and focus areas:
|
Planning
Team
|
By
September 8, 1998
|
October
13, 1998
|
|
Action
Team Leader Training:
|
Planning
Team
|
By
September 8, 1998
|
October
27, 1998
|
|
Approval
of revised Mission statement:
|
SSC/Planning
Team
|
|
November
12, 1998
|
|
Action
Team presentation of action plans to the Planning Team:
|
Planning
Team
|
By
November 10, 1998
|
March
18, 1999
|
|
Planning
Team presentation of recommended Long Range Plan to the Board:
|
Planning
Team
|
December
8, 1998
|
September
14, 1999
|
|
Implementation
of Action Plans:
|
Board
of Trustees, Administration, and School Site Council
|
From
December, 1998 on
|
See
action plan details
|
|
Preliminary
review of implementation:
|
School
Site Council
|
March,
1999
|
|
|
Annual
review of progress to Board:
|
School
Site Council
|
Every
year
|
|
|