THE BOLINAS-STINSON UNION SCHOOL DISTRICT
PROPOSED LONG-RANGE PLANNING PROCESS TIMELINE
Return to Table of Contents

Activity Responsible  Party Projected Date to be Accomplished Progress to Date/
Date Completed
Staff/parent/community survey:
  • Survey data compiled and presented to Board
School Site Council May 12, 1998 June 2, 1998
Designate Planning Team Composition
for presentation to the Board for approval.
School Site Council May 12, 1998 May 19, 1998
First Planning Team retreat:
  • Develop belief statements
  • Develop mission statement
  • Identify strengths and challenges of B/S SD
School Site Council

Planning Team
Planning Team
Planning Team

By June 6, 1998 June 19, 1998
Report to the Board on Beliefs, Mission and strengths and challenges: Planning Team June 9, 1998 June 23, 1998
Second Planning Team retreat:
  • Identify focus area
  • Compose action teams
Planning Team By July 10, 1998 September 10, 1998
Report to the Board on Action Teams and focus areas: Planning Team By September 8, 1998 October 13, 1998
Action Team Leader Training: Planning Team By September 8, 1998 October 27, 1998
Approval of revised Mission statement: SSC/Planning Team   November 12, 1998
Action Team presentation of action plans to the Planning Team: Planning Team By November 10, 1998 March 18, 1999
Planning Team presentation of recommended Long Range Plan to the Board: Planning Team December 8, 1998 September 14, 1999
Implementation of Action Plans: Board of Trustees, Administration, and School Site Council From December, 1998 on See action plan details
Preliminary review of implementation: School Site Council March, 1999  
Annual review of progress to Board: School Site Council Every year  



Return to Table of Contents
Long Range Planning Process Board Report January 11, 2000